The following roadworks are likely to cause some delays in the Chiswick area

Devonshire Road, Chiswick
26 June — 02 July
Delays likely - Road closure
Works description : LAY A NEW GAS SERVICE TO 94 DEVONSHIRE ROAD FROM THE MAIN
Responsibility for works: Cadent
Current status: Planned work about to start
Works reference:  AZ0071000928492

Kew Bridge Road, Brentford
27 June — 28 June
Works description : Partial duct crossing, TM ref CVU-C9-TM-0148 - COVID EXEMPTION
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference:  YG65200000264

Kew Road
27 June — 28 June
Delays likely - Lane closure
Works description : Removal of splitter island, TM ref CVU-C9-TM-0149 - COVID EXEMPTION
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference:  YG65200000265


Brackley Road, Chiswick
29 June — 22 September
Delays likely - Road closure
Works description : IMGA192466 Gas connection work at Junction. This is part of our MajorGas main replacement project on Chiswick High Road
Responsibility for works: Cadent
Current status: Planned work about to start
Works reference:  AZ0071000919135

Chiswick High Road (north Circular Road)
29 June — 03 July
Delays likely - Lane closure
Works description : LAY NEW SERVICE FROM MAIN IN CARRIAGEWAY
Responsibility for works: Cadent
Current status: Planned work about to start
Works reference:  AZ0071000945739

Great West Road, Brentford
29 June — 01 July
Delays likely - Lane closure
Works description : LANE CLOSURES TO ACCESS BT MANHOLES TO GULLY SUCK AND DESILT TO CLEAR BOCKAGE IN UNDERGROUND BT INFARSTUCTURE FOR THE INSTALLATION OF SUB DUCT AND FIBRE EXCAVATE IF NEEDED ONLY 1 TRAFFIC MANAGEMENT SET UP AT 1 TIME Contact details - Jon Maynard - 07734175389
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference:  BC005KN1W000CHISWICK-NS2

King Street, Hammersmith
29 June — 30 June
Delays likely - Traffic control (multi-way signals)
Works description : RATTLING COVER IN C/W- INTERNALLY REPORTED DEFECT IN C/W
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference:  MU288DM18603

Chiswick High Road
25 May — 11 September
Delays likely - Traffic control (multi-way signals)
Works description : Mains Replacement works. Replacing approx 574m 26" CI with 500mm PE bymeans of insertion. This will also include replacement and transfer of services.
Current status: Work in progress
Works reference:   AZ0071000872686

Barrowgate Road, Chiswick
26 May — 02 July
Delays likely - Road closure
Works description : Related to NationalGrid London Power Tunnels 1 Decommission Project. Decommission of Stop Joint 50/51, Link Box 50/51, DTS Kiosk 1, Pilot Kiosk 7 and installation of Monitoring pit 8 within FW & CW
Responsibility for works: NATIONAL GRID ELECTRICITY TRANSMISSION
Current status: Planned work about to start
Works reference:  HP003OCULPT1723123

Kew Bridge Road, Brentford
08 June — 30 June
Delays likely - Lane closure
Works description : Realign kerbs as part of construction of cycleway 9 construction, TM ref CVU-C9-TM-0145 - COVID EXEMPTION
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference:  YG65200000248

Source: www.roadworks.org

 

Like Reading Articles Like This? Help Us Produce More

This site remains committed to providing local community news and public interest journalism.

Articles such as the one above are integral to what we do. We aim to feature as much as possible on local societies, charities based in the area, fundraising efforts by residents, community-based initiatives and even helping people find missing pets.

We've always done that and won't be changing, in fact we'd like to do more.

However, the readership that these stories generates is often below that needed to cover the cost of producing them. Our financial resources are limited and the local media environment is intensely competitive so there is a constraint on what we can do.

We are therefore asking our readers to consider offering financial support to these efforts. Any money given will help support community and public interest news and the expansion of our coverage in this area.

A suggested monthly payment is £8 but we would be grateful for any amount for instance if you think this site offers the equivalent value of a subscription to a daily printed newspaper you may wish to consider £20 per month. If neither of these amounts is suitable for you then contact info@neighbournet.com and we can set up an alternative. All payments are made through a secure web site.

One-off donations are also appreciated. Choose The Amount You Wish To Contribute.

If you do support us in this way we'd be interested to hear what kind of articles you would like to see more of on the site – send your suggestions to the editor.

For businesses we offer the chance to be a corporate sponsor of community content on the site. For £30 plus VAT per month you will be the designated sponsor of at least one article a month with your logo appearing if supplied. If there is a specific community group or initiative you'd like to support we can make sure your sponsorship is featured on related content for a one off payment of £50 plus VAT. All payments are made through a secure web site.

June 27, 2020

Bookmark and Share