Forthcoming significant roadworks in the W4 area
The following roadworks are likely to cause some delays in the Chiswick area
Dates Confirmed for Start of First Phase of Works on Cycleway 9
Lane closures by Kew Bridge predicted to have major impact on traffic around Chiswick
A205 Chiswick High Road (north Circular Road), Chiswick
17 February — 28 February
Delays likely - Lane closure
Works description : Brentford Community Stadium WBS SC.2769.150.001 Resurfacing, kerbing and tactile paving Fw TM Plus Lane closure/narrowing
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference: YG429429851
|
A315,A205 Kew Bridge Road, Brentford
17 February — 24 February
Delays likely - Traffic control (multi-way signals)
Works description : Build 1 concrete chamber 1220mm x 680mm x 1665mm deep in Carriageway,Build 1 concrete chamber 1310mm x 610mm x 1265mm deep in Footway,Build 2 concrete chamber 2315mm x 737mm x 1565mm deep in Footway,Build 4 concrete chamber 915mm x 445mm x 965mm deep in Footway,Demolish 6 existing jointbox(s) or cabinet base(s),Install 15m of 2 poly ducts in Carriageway,Install 30m of 2 poly ducts in Footway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference: BC006TI001LC500289765107
|
A315,A205 Kew Bridge Road, Brentford
17 February — 28 February
Delays likely - Lane closure
Works description : Brentford Community Stadium WBS SC.2769.150.001 Resurfacing, kerbing and tactile paving Fw TM Plus Lane closure/narrowing
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference: YG429429850
|
B491 Turnham Green Terrace, Chiswick
17 February — 21 February
Delays likely - Traffic control (two-way signals)
Works description : NHH Plot 1, 1x25mm BP mtrd Supply in f/way and in Carriageway. Our intention is to complete the Permanent Reinstatement in the same phase
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference: MU307000809463320045-002
|
B491 Turnham Green Terrace, Chiswick
17 February — 23 February
Delays likely - Road closure
Works description : HH Plot 1-3, 3x25mm MDPE mtrd Supply FOR NEW WATER SUPPLY IN FW AND inCarriageway. Our intention is to complete the Permanent Reinstatement inthe same phase
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference: MU307000809490680045-001
|
A205,A315 Kew Road
15 February — 23 February
Delays likely - Lane closure
Works description : Cycleway 9 - main construction. Partially construct island 3 (TM ref: CVU-CS9-TM-0102-1)
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference: YG65200000184
|
A205,A315 Kew Road, Chiswick
14 February — 02 October
Delays likely - Lane closure
Works description : Cycle Superhighway 9 - initial notice for section 58 purposes and to cover works before/after construction is complete and prior to full opening while other phases are being completed.
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference: YG65200000074
A205,A315 Kew Road, Chiswick
15 February — 23 February
Delays likely - Lane closure
Works description : Cycleway 9 - main construction. Partially construct island 3 (TM ref: CVU-CS9-TM-0102-1)
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference: YG65200000184
A205,A315 Kew Road, Chiswick
15 February — 08 March
Delays likely - Lane closure
Works description : Cycleway 9 - main construction. Complete island 5 (CVU-CS9-TM-0100-1 weekends, CVU-CS9-TM-0101-1 weekdays). Linked permits Kew Bridge Road (YG65200000180) and northern footway (YG65200000180)
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference: YG65200000181
A205 Chiswick High Road (north Circular Road), Chiswick
14 February — 02 October
Delays likely - Lane closure
Works description : Cycle Superhighway 9 - initial notice for section 58 purposes and to cover works before/after construction is complete and prior to full opening while other phases are being completed.
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference: YG65200000077
A307,A205 Kew Road, Kew
14 February — 02 October
Delays likely - Lane closure
Works description : Cycle Superhighway 9 - initial notice for section 58 purposes and to cover works before/after construction is complete and prior to full opening while other phases are being completed.
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference: YG65200000075
A315,A205 Kew Bridge Road, Brentford
14 February — 02 October
Delays likely - Lane closure
Works description : Cycle Superhighway 9 - initial notice for section 58 purposes and to cover works before/after construction is complete and prior to full opening while other phases are being completed.
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference: YG65200000076
A315,A205 Kew Bridge Road, Brentford
15 February — 24 February
Delays likely - Traffic control (multi-way signals)
Works description : Build 1 concrete chamber 1220mm x 680mm x 1665mm deep in Carriageway,Build 1 concrete chamber 1310mm x 610mm x 1265mm deep in Footway,Build 2 concrete chamber 2315mm x 737mm x 1565mm deep in Footway,Build 4 concrete chamber 915mm x 445mm x 965mm deep in Footway,Demolish 6 existing jointbox(s) or cabinet base(s),Install 15m of 2 poly ducts in Carriageway,Install 30m of 2 poly ducts in Footway Responsibility for works: Openreach
Current status: Planned work about to start
Works reference: BC006TI001LC500289765108
A315,A205 Kew Bridge Road, Brentford
15 February — 24 February
Delays likely - Traffic control (multi-way signals)
Works description : Build 1 concrete chamber 1220mm x 680mm x 1665mm deep in Carriageway,Build 1 concrete chamber 1310mm x 610mm x 1265mm deep in Footway,Build 2 concrete chamber 2315mm x 737mm x 1565mm deep in Footway,Build 4 concrete chamber 915mm x 445mm x 965mm deep in Footway,Demolish 6 existing jointbox(s) or cabinet base(s),Install 15m of 2 poly ducts in Carriageway,Install 30m of 2 poly ducts in Footway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference: BC006TI001LC500289765109
A315 Chiswick High Road, Chiswick
12 February — 18 February
Delays likely - Lane closure
Works description : Trial holes and carriageway cores to evaluate existing highway construction as part of design evaluation of Cycle Superhighway 9 (Hounslow section). TM attached. Trial holes max 1 day at each location, cores maximum of 2 hours at each location
Responsibility for works: Transport for London
Current status: Planned work about to start
Works reference: YG65200000161
A315,A205 Kew Bridge Road, Brentford
10 February — 21 February
Delays likely - Traffic control (multi-way signals)
Works description : Build 1 concrete chamber 1220mm x 680mm x 1665mm deep in Carriageway,Build 1 concrete chamber 1310mm x 610mm x 1265mm deep in Footway,Build 2 concrete chamber 2315mm x 737mm x 1565mm deep in Footway,Build 4 concrete chamber 915mm x 445mm x 965mm deep in Footway,Demolish 6 existing jointbox(s) or cabinet base(s),Install 15m of 2 poly ducts in Carriageway,Install 30m of 2 poly ducts in Footway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference: BC006TI001LC500289765101 |
Source: www.roadworks.org
Like Reading Articles Like This? Help Us Produce More
This site remains committed to providing local community news and public interest journalism.
Articles such as the one above are integral to what we do. We aim to feature as much as possible on local societies, charities based in the area, fundraising efforts by residents, community-based initiatives and even helping people find missing pets.
We've always done that and won't be changing, in fact we'd like to do more.
However, the readership that these stories generates is often below that needed to cover the cost of producing them. Our financial resources are limited and the local media environment is intensely competitive so there is a constraint on what we can do.
We are therefore asking our readers to consider offering financial support to these efforts. Any money given will help support community and public interest news and the expansion of our coverage in this area.
A suggested monthly payment is £8 but we would be grateful for any amount for instance if you think this site offers the equivalent value of a subscription to a daily printed newspaper you may wish to consider £20 per month. If neither of these amounts is suitable for you then contact info@neighbournet.com and we can set up an alternative. All payments are made through a secure web site.
One-off donations are also appreciated. Choose The Amount You Wish To Contribute.
If you do support us in this way we'd be interested to hear what kind of articles you would like to see more of on the site – send your suggestions to the editor.
For businesses we offer the chance to be a corporate sponsor of community content on the site. For £30 plus VAT per month you will be the designated sponsor of at least one article a month with your logo appearing if supplied. If there is a specific community group or initiative you'd like to support we can make sure your sponsorship is featured on related content for a one off payment of £50 plus VAT. All payments are made through a secure web site.
|
February 15, 2020
|