The following roadworks are likely to cause some delays in the Chiswick area

Lane Closures on North Circular Near Chiswick Roundabout to Resume
Work on improving Gunnersbury Avenue safety to last through to Summer

chiswick roadworks

A315 Chiswick High Road, Chiswick

17 January — 17 January

Delays likely Traffic control (multi-way signals)

Works description: S81 EMERGENCY COVER REPLACEMEN--WORKS INTENDED TO INCLUDE FIRST TIME PERMANENT REINSTATEMENT WITHIN SAME PHASE

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU026002141FYLY--000001

M4

15 January — 16 January

Delays likely Road closure

Works location: Slip Closure Westbound.

Works description: M4 Jct 2 Westbound Exit Slip. Slip Closure for pier monitoring works. Diversion via HE Network.

Responsibility for works: Highways England

Current status: Planned work about to start

Works reference: 76257

M4

16 January — 17 January

Delays likely Road closure

Works location: Slip Closure Westbound.

Works description: M4 Jct 2 Westbound Exit Slip. Slip Closure for pier monitoring works. Diversion via HE Network.

Responsibility for works: Highways England

Current status: Planned work about to start

Works reference: 76257

Great West Road, Hammersmith

14 January — 15 January

Delays likely Lane closure

Works location: Unknown

Works description: Footway Patching repairs

Responsibility for works: Transport for London

Current status: Planned work about to start

Works reference: YG430349708

A315 King Street, Hammersmith

07 January — 22 June

Delays likely Traffic control (multi-way signals)

Works description: IMGA191090. MAJOR LARGE DIAMETER MAINS REPLACEMENT WORKS TO TAKE PLACE.ABANDON 722M OF METALLIC MAIN AND REPLACE IT WITH PE MAIN.INSERTION METHOD TO BE USED, NEW MAIN TO BE SLEEVED INSIDE THE OLD TOREDUCE EXCAVATION. STORAGE CONTAINER & WELFARE UNIT TO BE USED ON SITE.

Responsibility for works: Cadent

Current status: Planned work about to start

Works reference: AZ0071000752541

A406 Gunnersbury Avenue (north Circular Road)

07 January — 05 March

Delays likely Lane closure

Works description: Phase 1a - 2c Utility works, drainage and re-profiling works.

Responsibility for works: Transport for London

Current status: Advanced planning

Works reference: YG432343386

A4 Great West Road, Brentford

07 January — 16 February

Delays likely Lane closure

Works description: A4 Pier monitoring - removal of delaminating concrete. Lane 3 and 2 closure east and westbound. Diversion from M4 Jct 2 to Jct 3, A312 southbound and A4 eastbound..

Responsibility for works: Highways England

Current status: Planned work about to start

Works reference: FN59343449

B4491,A4000 Gunnersbury Lane, Acton

14 December — 13 February

Delays likely Traffic control (Stop/Go boards)

Works description: Temporary Structure Licence - Crane

Responsibility for works: Ealing

Current status: Planned work about to start

Works reference: DV008TS0387

A406 Gunnersbury Avenue (North Circular Road)

24 November — 22 February

Delays likely Lane closure

Works description: Phase 1a - 4 Utility works, drainage and re-profiling works.

Responsibility for works: Transport for London

Current status: Advanced planning

Works reference: YG432334046

Source: www.roadworks.org