Forthcoming significant roadworks in the W4 area
The following roadworks are likely to cause some delays in the Chiswick area
Nine Month Delay to Gunnersbury Avenue Roadworks
Power Road bridge project lane closures to continue until autumn 2018
A315 Chiswick High Road, Chiswick |
29 September — 11 October |
Delays likely Road closure |
Works description: Excavate, rebuild frame and cover and reinstate on behalf of Vodafone while working under a road nclosure |
Responsibility for works: Vodafone |
Current status: Planned work about to start |
Works reference: NX50218JHG111 |
A4 Great West Road, Brentford |
01 October — 08 October |
Delays likely Lane closure |
Works description: Install dual lay HV duct in F/W. |
Responsibility for works: GAS TRANSPORTATION CO LTD |
Current status: Planned work about to start |
Works reference: ZP011P91252N00186191/R16 |
|
B350 Lonsdale Road, Barnes |
01 October — 02 October |
Delays likely Traffic control (two-way signals) |
Works description: S81 PLANNED COVER REPLACEMENT--WORKS INTENDED TO INCLUDE FIRST TIME PERMANENT REINSTATEMENT WITHIN SAME PHASE |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU026002251XYNR--000001 |
|
M4 |
01 October — 02 October |
Delays likely Road closure |
Works location: Slip Closure Westbound. |
Works description: M4 Jct 2 Westbound Entry Slip Road Closure for maintenance works. Diversion via Local Authority Network |
Responsibility for works: Highways England |
Current status: Planned work about to start |
Works reference: 71488 |
|
M4 |
01 October — 02 October |
Delays likely Road closure |
Works location: entry slip eastbound. |
Works description: M4 Jct 2 eastbound entry slip closure for routine maintenance. Diversion via Local Authority network. |
Responsibility for works: Highways England |
Current status: Planned work about to start |
Works reference: 54771 |
|
M4 |
02 October — 03 October |
Delays likely Road closure |
Works location: entry slip eastbound. |
Works description: M4 Jct 2 eastbound entry slip closure for routine maintenance. Diversion via Local Authority network. |
Responsibility for works: Highways England |
Current status: Planned work about to start |
Works reference: 54771 |
|
M4 |
02 October — 03 October |
Delays likely Road closure |
Works location: Slip Closure Westbound. |
Works description: M4 Jct 2 Westbound Entry Slip Road Closure for maintenance works. Diversion via Local Authority Network |
Responsibility for works: Highways England |
Current status: Planned work about to start |
Works reference: 71488 |
|
A406 Gunnersbury Avenue, Ealing |
03 October — 06 October |
Delays likely Contra-flow |
Works location: Unknown |
Works description: lay new gas main and service approx. 2m in f/way |
Responsibility for works: Fulcrum Pipelines Limited |
Current status: Planned work about to start |
Works reference: WY001NSA00020881 |
|
Brackenbury Road, Hammersmith |
03 October — 04 October |
Delays likely Traffic control (Stop/Go boards) |
Works location: Unknown |
Works description: Thames Water need to carry out works on the water valve. Stop & Go boards will be installed to allow these works to be carried out. Minor Works, No Excavation. |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU150WO-23818737/TW |
|
M4 |
03 October — 04 October |
Delays likely Road closure |
Works location: Slip Closure Westbound. |
Works description: M4 Jct 2 Westbound Entry Slip Road Closure for maintenance works. Diversion via Local Authority Network |
Responsibility for works: Highways England |
Current status: Planned work about to start |
Works reference: 71488 |
|
M4 |
03 October — 04 October |
Delays likely Road closure |
Works location: entry slip eastbound. |
Works description: M4 Jct 2 eastbound entry slip closure for routine maintenance. Diversion via Local Authority network. |
Responsibility for works: Highways England |
Current status: Planned work about to start |
Works reference: 54771 |
|
A315 King Street, Hammersmith |
14 September — 02 October |
Delays likely Road closure |
Works description: TEST |
Responsibility for works: Hammersmith and Fulham |
Current status: Advanced planning |
Works reference: FE900308943 |
|
Fishers Lane, Chiswick |
01 September — 31 October |
Delays likely Road closure |
Works description: Carriageway resurfacing, |
Responsibility for works: Ealing |
Current status: Planned work about to start |
Works reference: DV00665000563 |
|
B408 Paddenswick Road, Hammersmith |
20 August — 01 October |
Delays likely Traffic control (multi-way signals) |
Works description: CONSTRUCTION OF A MINI PUMPING STATION (FLIP) IN THE FOOTWAY & CARRIAGEWAY |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU895MGJV/FLIPS/193360A |
|
B491 Southfield Road, Chiswick |
01 August — 31 October |
Delays likely Road closure |
Works description: Carriageway resurfacing, |
Responsibility for works: Ealing |
Current status: Planned work about to start |
Works reference: DV00665000541 |
|
Hardwicke Road, Chiswick |
18 June — 31 October |
Delays likely Road closure |
Works description: Microsurfacing |
Responsibility for works: Ealing |
Current status: Planned work about to start |
Works reference: DV00665000529 |
|
Gunnersbury Avenue (North Circular Road) |
7 Jun 2017 - 16 Nov 2018 |
Delays likely Lane Closure |
Works description:1 northbound lane closed, one running lane maintained northbound and two southbound. Traffic lanes will be realigned on the carriageway to suit phases of work during demolition of the main bridge. Lanes will first be slewed to the east and then to the west. |
Responsibility for works: Transport For London |
Current status: Work in progress |
Source: www.roadworks.org
October 5, 2018
|