Traffic Delays Likely in Chiswick

Forthcoming significant roadworks in the W4 area

 
Participate

Bookmark and Share

Traffic and Travel in Chiswick

Sign up for our weekly Chiswick newsletter

Comment on this story on the

The following roadworks are likely to cause some delays in the Chiswick area

chiswick roadworks

Hammersmith Bridge to Close for Four Days in August
Cars diverted and bus routes shortened for repairs ahead of major refurbishment - 20 August - 23 August

Nine Month Delay to Gunnersbury Avenue Roadworks
Power Road bridge project lane closures to continue until autumn 2018

A205 Chiswick High Road (north Circular Road), Chiswick

22 August — 24 August

Delays likely Lane closure

Works description: CARRIAGEWAY RESURFACING

Responsibility for works: Transport for London

Current status: Planned work about to start

Works reference: YG430321238

A315 Chiswick High Road, Chiswick

22 August — 25 August

Delays likely Traffic control (multi-way signals)

Works description: SEWER CLEANING - PLANNED

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU026002139RYBY--000007

M4

23 August — 24 August

Delays likely Road closure

Works location: Slip Closure Westbound.

Works description: M4 Jct 2 Westbound Entry Slip road Closure for resurfacing works. Diversion via Local Authority Network

Responsibility for works: Highways England

Current status: Planned work about to start

Works reference: 62998

Sutton Court Road, Chiswick

18 August — 03 September

Delays likely Traffic control (multi-way signals)

Works location: Unknown

Works description: new customer water supply 1x32mm MDPE mtrd, works in the footway and inCarriageway. Our intention is to complete the Permanent Reinstatement inthe same phase

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU307000806928770045-001

A3000 Heathfield Terrace, Chiswick

20 August — 23 August

Delays likely Traffic control (give & take)

Works description: Excavation works to install duct and build associated chambers for fibre optic cable installation.

Responsibility for works: GLOBAL CROSSING (UK) TELECOMMUNICATIONS

Current status: Planned work about to start

Works reference: RT003CHISWICK-003294/01

A306 Castelnau, Barnes

20 August — 24 August

Delays likely Traffic control (Stop/Go boards)

Works description: Carry out carriageway patching repairs. Ch8 reqd T.M reqd Stop/Go

Responsibility for works: Richmond upon Thames

Current status: Planned work about to start

Works reference: KP601WKS2168309A

A4000,A4020 High Street, Acton

20 August — 29 August

Delays likely Traffic control (multi-way signals)

Works description: Permit for TM associated to LP551-S30001814 works. NIL EXCAVATION

Responsibility for works: Scottish and Southern Power Distribution

Current status: Planned work about to start

Works reference: LP551S30001968

A4020 Uxbridge Road, Acton

20 August — 29 August

Delays likely Traffic control (multi-way signals)

Works description: for traffic light head only associated with LP551S30001814

Responsibility for works: Scottish and Southern Power Distribution

Current status: Planned work about to start

Works reference: LP551S30001969

B408 Paddenswick Road, Hammersmith

20 August — 01 October

Delays likely Traffic control (multi-way signals)

Works description: CONSTRUCTION OF A MINI PUMPING STATION (FLIP) IN THE FOOTWAY & CARRIAGEWAY

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU895MGJV/FLIPS/193360A

B4491,A4000 Gunnersbury Lane, Acton

20 August — 29 August

Delays likely Traffic control (multi-way signals)

Works description: Excavate in footway for mains joint for new supply. Backfill & reinstate.

Responsibility for works: Scottish and Southern Power Distribution

Current status: Planned work about to start

Works reference: LP551S30001814

A406 Gunnersbury Avenue (North Circular Road)

04 August — 22 September

Delays likely Lane closure

Works description: 24 hour Vario Guard Closure a per works programme. Remove kerbs/ excavate grass verge area to formation level / remove existing drainage. install new drainage/ relay kerbs/ backfill to formation level /reprofiling grass verge area/install new knee rail/install new PCC edgins / install new tactiles& ASP paving

Responsibility for works: Transport for London

Current status: Advanced planning

Works reference: YG432311016

A406 Gunnersbury Avenue (North Circular Road)

04 August — 22 September

Delays likely Lane closure

Works description: 24 hour Vario Guard Closure a per works programme. Remove kerbs/ excavate grass verge area to formation level / remove existing drainage. install new drainage/ relay kerbs/ backfill to formation level /reprofiling grass verge area/install new knee rail/install new PCC edgins / install new tactiles& ASP paving

Responsibility for works: Transport for London

Current status: Advanced planning

Works reference: YG432307843

B491 Southfield Road, Chiswick

01 August — 31 October

Delays likely Road closure

Works description: Carriageway resurfacing,

Responsibility for works: Ealing

Current status: Planned work about to start

Works reference: DV00665000541

Hardwicke Road, Chiswick

18 June — 31 October

Delays likely Road closure

Works description: Microsurfacing

Responsibility for works: Ealing

Current status: Planned work about to start

Works reference: DV00665000529

Gunnersbury Avenue (North Circular Road)

7 Jun 2017 - 16 Nov 2018

Delays likely Lane Closure

Works description:1 northbound lane closed, one running lane maintained northbound and two southbound. Traffic lanes will be realigned on the carriageway to suit phases of work during demolition of the main bridge. Lanes will first be slewed to the east and then to the west.

Responsibility for works: Transport For London

Current status: Work in progress


Source: www.roadworks.org

August 23, 2018

Bookmark and Share