Forthcoming significant roadworks in the W4 area
The following roadworks are likely to cause some delays in the Chiswick area
Acton Lane |
20 April — 21 April |
Delays likely Traffic control (two-way signals) |
Works location: - |
Works description: - |
Responsibility for works: Thames Water |
Current status: Planned work about to start |
Grove Park Road, Chiswick |
14 April — 28 April |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Planned work about to start |
|
|
Fishers Lane, Chiswick |
10 April — 19 April |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Planned work about to start |
|
Dukes Avenue, Chiswick |
17 April — 09 May |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Thames Water |
Current status: Planned work about to start |
Gunnersbury Avenue (North Circular Road) |
31 March — 13 May |
Delays likely Contra-flow |
Works location: - |
Works description: - |
Responsibility for works: Transport For London |
Current status: Planned work about to start |
Gunnersbury Avenue (North Circular Road) |
05 April — 13 May |
Delays likely Contra-flow |
Works location: - |
Works description: - |
Responsibility for works: Transport For London |
Current status: Planned work about to start |
|
Kew Road, Kew |
01 April — 01 May |
Delays likely Traffic control (two-way signals) |
Works location: - |
Works description: - |
Responsibility for works: Transport For London |
Current status: Advanced planning |
Source: www.roadworks.org