Fisher's Lane To Be Closed For Four Weeks
A315 Chiswick High Road, Chiswick |
16 October — 16 October |
|
|
Delays likely Lane closure |
|
Works location: A315 |
|
|
Works description: 25/005 Tel0061414 - Repair Damaged Traffic Signal Detection By Slotcutting Bp1.2.3 Loops, 0800 - 1200, W/B Lane 2 Closed Only, W/B Traffic Flow To Be Maintained Using The Bus Lane. Ttro Reference: Tmo/T057-16 |
|
|
Responsibility for works: Transport For London |
|
|
Current status: Planned work about to start |
|
|
|
|
Bollo Lane, Acton |
16 October — 16 October |
|
|
Delays likely Road closure |
|
Works location: Level Crossing |
|
|
Works description: Track Inspection Through Level Crossing Working From 01.10-09.00... |
|
|
Responsibility for works: Network Rail Infrastructure Ltd |
|
|
Current status: Advanced planning |
|
|
|
|
Burlington Lane, Chiswick |
16 October — 16 October |
|
|
Delays likely Road closure |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Transport For London |
|
|
Current status: Planned work about to start |
|
|
|
Rusthall Avenue, Chiswick |
12 September — 17 October |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: National Grid Gas Plc |
Current status: Planned work about to start |
|
Clifford Avenue, Richmond |
14 October — 15 October |
|
|
Delays likely Lane closure |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Transport For London |
|
|
Current status: Planned work about to start |
|
|
A307/A205 Kew Road, Kew |
05 September — 06 November |
Delays likely Contra-flow |
Works location: A307/A205 |
Works description: Refurbishment And Replacement Of Service Bay Cover Slabs |
Responsibility for works: Transport For London |
Current status: Planned work about to start |
|