A4 Cedars Road, Chiswick

25 July — 13 August

Delays likely Lane closure

Works location: A4

Works description: Removing Existing Safety Barrier And Replacing With Flexibeam System

Responsibility for works: Transport For London

Current status: Planned work about to start

A4 Great West Road, Brentford

25 July — 05 August

Delays likely Lane closure

Works location: A4

Works description: 22:00 To 05:30hrs. Lane 1 And 2 Closure Or A Lane 3 And 2 Closure Eastbound For Delaminated Concrete Surveys Of The A4 Piers (Pier 31 To Pier 1)

Responsibility for works: Highways England

Current status: Advanced planning

A4 Great West Road, Chiswick

04 August — 05 August

Delays likely Lane closure

Works location: A4

Works description: Block Closure Wb# Testing Lights& Bollards, Bulk Clean & Change, Sweeping, Gully & Beany Block Cleaning, Barrier Works, Grass Cutting, Sign Cleaning, Debris Patrols

Responsibility for works: Transport For London

Current status: Planned work about to start

A315/A205 Kew Bridge Road, Brentford

23 July — 07 August

Delays likely Lane closure

Works location: A315/A205

Works description: Excavate Of 30" Water Main To Remove A Defect Section Of Approx 40m In Southbound Carriageway, Working For Optimise On Behalf Of Thames Water

Responsibility for works: Thames Water

Current status: Planned work about to start

Shirley Road, Chiswick

18 July — 15 August

Delays likely Road closure

Works location: -

Works description: -

Responsibility for works: Ealing London Borough Council

Current status: Advanced planning

A406 Gunnersbury Avenue (North Circular Road)

11 July — 21 August

Delays likely Lane closure

Works location: A406

Works description: Closure Of One Northbound Lane To Facilitate The Diversion Of Thames Water Main Onto Service Bridge. Northbound Traffic Flow Maintained In Lane Two

Responsibility for works: Transport For London

Current status: Planned work about to start

Devonshire Road, Chiswick

04 July — 09 August

Delays likely Road closure

Works location: -

Works description: -

Responsibility for works: National Grid Gas Plc

Current status: Planned work about to start

A307/A205 Kew Road, Kew

01 August — 25 September

Delays likely Road closure

Works location: A307/A205

Works description: Installation Of Temporary Barriers, Refurbishment And Replacement Of Service Bay Cover Slabs

Responsibility for works: Transport For London

Current status: Advanced planning

A4 Great West Road, Brentford

01 August — 03 August

Delays likely Lane closure

Works location: A4

Works description: Block Closure Wb# Testing Lights& Bollards, Bulk Clean & Change, Sweeping, Gully & Beany Block Cleaning, Barrier Works, Grass Cutting, Sign Cleaning, Debris Patrols

Responsibility for works: Transport For London

Current status: Planned work about to start

Ravenscourt Gardens, Hammersmith

01 August — 03 August

Delays likely Road closure

Works location: -

Works description: -

Responsibility for works: Thames Water

Current status: Planned work about to start

Source: www.roadworks.org

August 4, 2016