Forthcoming significant roadworks in the W4 area
The following roadworks are likely to cause some delays in the Chiswick area: Some may not cause delays but residents may be interested to know of work going on in advance.
Bollo Bridge Road, Acton |
21 March — 04 April |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Ealing London Borough Council |
Current status: Planned work about to start |
|
Clarence Road, Chiswick |
21 March — 24 March |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Advanced planning |
|
Pyrmont Road, Chiswick |
23 March — 29 March |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Advanced planning |
Clarence Road, Chiswick |
21 March — 24 March |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Advanced planning |
|
Oxford Gardens, Chiswick |
22 March — 29 March |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Advanced planning |
|
A315 King Street |
15 March — 30 March |
Delays likely Lane closure |
Works location: A315 |
Works description: Dig Down And Locate The Water Main And Check On The Condition And Take A Measurement. |
Responsibility for works: Thames Tideway Tunnel Ltd |
Current status: Planned work about to start |
|
A406 Gunnersbury Avenue (North Circular Road) |
11 January — 28 March Lane closure |
Delays likely due to Streetworks
Ti Modernisation Scheme/ Pedestrian Crossing Lane 1 Switch To Lane 2 Closure And Back To Back Lane 2'S Around Ped Islands. Works To Finish 16/12/15 And Continue 04/01/16 24/7 Fw 2100 - 0530 Cw at A406 |
Responsibility: Transport For London |
EToN status: Planned work about to start |
|
A406 Gunnersbury Avenue |
11 January — 28 March Lane closure |
Delays likely due to Streetworks
Ti Modernisation Scheme/ Pedestrian Crossing Lane 1 Switch To Lane 2 Closure And Back To Back Lane 2'S Around Ped Islands. Works To Finish 16/12/15 And Continue 04/01/16 24/7 Fw 2100 - 0530 Cw. No Works To Take Place Night Of 05/02 - 06/02/16. at A406 |
Responsibility: Transport For London |
EToN status: Planned work about to start |
|
B4491/A4000 Gunnersbury Lane |
11 January — 28 March Lane closure |
Delays likely due to Streetworks
Ti Modernisation Scheme/ Pedestrian Crossing Lane 1 Switch To Lane 2 Closure And Back To Back Lane 2'S Around Ped Islands. Works To Finish 16/12/15 And Continue 04/01/16 2000 - 0500(F/W) 2200 - 0500 (C/W) at B4491/A4000 |
Responsibility: Transport For London |
EToN status: Planned work about to start |
|
B4491 Popes Lane |
11 January — 28 March Lane closure |
Delays likely due to Streetworks
Ti Modernisation Scheme/ Pedestrian Crossing Lane 1 Switch To Lane 2 Closure And Back To Back Lane 2'S Around Ped Islands. Works To Finish 16/12/15 And Continue 04/01/16 2000 - 0500 (F/W) 2200 - 0500 (C/W) Tman N1501164-001-W001 at B4491 |
Responsibility: Transport For London |
EToN status: Planned work about to start |
|
Source: www.roadworks.org
March 24, 2016
|