Planned roadworks in the W4 area
The following roadworks are likely to cause some delays in the Chiswick area: Some may not cause delays but residents may be interested to know of work going on in advance.
Spring Grove, Chiswick |
07 December — 04 January 2016 Road closure |
Delays likely due to Streetworks
- at - |
Responsibility: Thames Water |
EToN status: Advanced planning |
A4 Great West Road, Brentford |
04 January — 05 January Lane closure |
Delays likely due to Streetworks
Wp Block Closure Wb# Testing Lights& Bollards, Bulk Clean & Change, Sweeping, Gully & Beany Block Cleaning, Barrier Works, Grass Cutting, Sign Cleaning, Debris Patrols. Nearside Lane Closures With Offside Lane Running 22:30-05:00 at A4 |
Responsibility: Transport For London |
EToN status: Planned work about to start |
|
British Grove, Chiswick |
04 January — 17 January Road closure |
Delays likely due to Streetworks
- at - |
Responsibility: euNetworks |
EToN status: Planned work about to start |
|
A4 Great West Road, Brentford |
05 January — 06 January Lane closure |
Delays likely due to Streetworks
Cpp Block Closure Wb# Testing Lights& Bollards, Bulk Clean & Change, Sweeping, Gully & Beany Block Cleaning, Barrier Works, Grass Cutting, Sign Cleaning, Debris Patrols. Offside Lane Closures With Nearside Lane Running 22:30-05:00 at A4 |
Responsibility: Transport For London |
EToN status: Planned work about to start |
Source: www.roadworks.org