The following roadworks are likely to cause some delays in the Chiswick area:

Putney Bridge to Reopen on September 26th

Major Work On Chiswick Bridge

 

B409 Bath Road, Chiswick

17 September — 19 September

Delays likely Traffic control (two-way signals)

Works location: B409

Works description: S81 Planned Cover Replacement--Works Intended To Include First Time Permanent Reinstatement Within Same Phase

Responsibility for works: Thames Water

Current status: Planned work about to start

Great Chertsey Road, Chiswick

17 September — 03 December

Delays likely Traffic control (two-way signals)

Works location: -

Works description: -

Responsibility for works: Transport For London

Current status: Advanced planning

A205 Chiswick High Road (North Circular Road)

20 September — 21 September

Delays likely Lane closure

Works location: A205

Works description: Exchange A Faulty Thames Water Network Valve In Carriageway. Ourintention Is To Complete The Permanent Reinstatement In The Same Phase

Responsibility for works: Thames Water

Current status: Planned work about to start ~

A4 Cedars Road, Chiswick

15 September — 21 September

Delays likely Lane closure

Works location: A4

Works description: Safety Camera Renewal Scheme - Carriageway& Footway Works - Replacement Of Existing Safety Camera Pole In F/W Plus Slot Cut And Install New Sensors In Carriageway

Responsibility for works: Transport For London

Current status: Planned work about to start

 

Kew Bridge Road, Brentford

15 September — 26 September

Delays likely Lane closure

Works location: -

Works description: -

Responsibility for works: Thames Water

Current status: Planned work about to start

Great Chertsey Road, Chiswick

18 September — 05 November

Delays likely Traffic control (multi-way signals)

Works location: -

Works description: -

Responsibility for works: Transport For London

Current status: Planned work about to start

Stile Hall Gardens, Chiswick

15 September — 28 September

Delays likely Road closure

Works location: -

Works description: -

Responsibility for works: Thames Water

Current status: Planned work about to start

B4491 Popes Lane, Ealing
24 July - 10 January 2015
Delays likely Lane closure
Location : B4491 Description : To excavate trench lay ducting for future cable lay, jointbays will be required and install ducting for 132KV and will replace the exisiting oil filled cables, jointbays will be app 12 meters by 4 meters wide, the route will be ducted and jointbays dug seperately, works will involve weekend works and nights if requested, mostly lane closure, small pinchpoint poss closure Traffic lights, etc

Great West Road, Brentford

09 June — 31 October

Delays likely Lane closure

Works location: -

Works description: -

Responsibility for works: Transport For London

Current status: Advanced planning

Gunnersbury Avenue (North Circular Road)

02 June — 30 November 2015

Delays likely Lane closure

Works location: -

Works description: -

Responsibility for works: Transport For London

Current status: Advanced planning

 