Planned roadworks in the W4 area
The following roadworks are likely to cause some delays in the Chiswick area:
Hogarth Flyover To Be Closed For Summer
Putney Bridge Closure Date Confmed
Major Work Begins On Chiswick Bridge
A316 Burlington Lane, Chiswick |
23 August — 29 August |
Delays likely Lane closure |
Works location: A316 |
Works description: Instal Of Clamps And Removal Of Scaffolding Sat 2300hrs - 0800hrs Lane 1 And 2 Sun 2300hrs - 0800hrs (Note: Mon Bank Holiday) Lane 1 And 2 Mon 2300hrs - 0500hrs Lane 1 And 2 Tue - Thurs 0100hrs - 0500hrs (Note: Clash With Hfo Closures) Lane 2 And 3 Lane Closures On Hogarth Rab And Approaches Tman Ref N1400589-001-W001 |
Responsibility for works: Transport For London |
Current status: Planned work about to start |
|
|
A4 Great West Road, Chiswick |
23 August — 29 August |
Delays likely Lane closure |
Works location: A4 |
Works description: Instal Of Clamps And Removal Of Scaffolding Sat 2300hrs - 0800hrs Lane 1 And 2 Sun 2300hrs - 0800hrs (Note: Mon Bank Holiday) Lane 1 And 2 Mon 2300hrs - 0500hrs Lane 1 And 2 Tue - Thurs 0100hrs - 0500hrs (Note: Clash With Hfo Closures) Lane 2 And 3 Lane Closures On Hogarth Rab And Approaches Tman Ref N1400589-001-W001 |
Responsibility for works: Transport For London |
Current status: Planned work about to start |
|
|
Garth Road, Chiswick |
20 August — 29 August |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Planned work about to start
|
|
Edensor Gardens, Chiswick |
21 August — 01 September |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Planned work about to start
|
Spencer Road, Chiswick |
22 August — 04 September |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Planned work about to start |
Devonshire Gardens, Chiswick |
26 August — 05 September |
|
|
Delays likely Road closure |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Hounslow London Borough Council |
|
|
Current status: Advanced planning |
|
|
B4491 Popes Lane, Ealing |
24 July - 10 January 2015 |
Delays likely Lane closure |
Location : B4491 Description : To excavate trench lay ducting for future cable lay, jointbays will be required and install ducting for 132KV and will replace the exisiting oil filled cables, jointbays will be app 12 meters by 4 meters wide, the route will be ducted and jointbays dug seperately, works will involve weekend works and nights if requested, mostly lane closure, small pinchpoint poss closure Traffic lights, etc |
|
B490 Acton Lane, Chiswick -POSTPONED |
20 August — 04 September |
Delays likely Road closure |
Works location: B490 |
Works description: Imga140635 (Mark Branch) Abandon 9 Metres Of 6" Si And Insert/Open Cut 9metres Of 90mm Pe Main. No Services To Relay/Transfer |
Responsibility for works: National Grid Gas Plc |
Current status: Advanced planning
|
Great West Road, Brentford |
09 June — 31 October |
Delays likely Lane closure |
Works location: - |
Works description: - |
Responsibility for works: Transport For London |
Current status: Advanced planning
|
Gunnersbury Avenue (North Circular Road) |
02 June — 30 November 2015 |
Delays likely Lane closure |
Works location: - |
Works description: - |
Responsibility for works: Transport For London |
Current status: Advanced planning
|
|
Source: www.roadworks.org
August 26, 2014
|